Governor Carlos M. Padilla conducts a 3-day inspection of various infrastructure projects

Governor Carlos M. Padilla conducts a 3-day inspection of various infrastructure projects on August 20, 21, and 23, 2021 in the municipalities of Kasibu, Dupax del Sur, Bagabag, Diadi, and Quezon.

The governor was accompanied by staff from the Provincial Engineering Office led by Provincial Engineer Nestor Velasco and members of the Nueva Vizcaya Press Club.

The funds for the projects are from the P1 Billion Land Bank of the Philippines loan package.

August 20, 2021
Kasibu
Upgrading of Jct. National-Bua-Bulala-Muta-Macabenga Road.
Appropriation: P180M
Contract Cost: P166,383,965.78
Length: 10,458.723 mts.
Width: 6.10 mts.
Contractor: Phranaret Construction
Duration: 384 Calendar days
Date Started: July 8, 2021
Expiry Date: July 26, 2022

August 21, 2021
Dupax del Sur & Aritao
Upgrading of Palabotan-Banila-Caino-Anayo-Canarem Road.
Appropriation: P248.7M
Contract Cost: P234,089,204.25
Length: 14,457.69 mts.
Width: 6.10 mts.
Contractor: Omengan Construction and Development Corporation
Duration: 540 Calendar days
Date Started: July 8, 2021
Expiry Date: December 29, 2022

Dupax del Sur
Upgrading of Dupax del Sur-Iiyo-Carolotan Road.
Appropriation: P83M
Contract Cost: P79,451,833.60
Length: 4,049.07 mts.
Width: 6.10 mts.
Contractor: Bugani Construction and Enterprises Inc./Triple P Construction (JOINT Venture)
Duration: 384 Calendar days
Date Started: July 8, 2021
Expiry Date: January 15, 2022

August 23, 2021
Bagabag
Concreting of Bagabag District Hospital Access Road (Entry and Exit).
Appropriation: P4.8M
Contract Cost: P4,580,610.17
Length: 181.155 mts.
Width: 6.10 mts.
Contractor: Ambaguio Builders
Duration: 46 Calendar days
Revised Contract Duration: 71 Calendar days
Date Started: July 8, 2021
Expiry Date: August 23, 2022
Revised Expiry Date: September 17, 2021

Diadi
Upgrading of CVR Nagsabaran-Decabacan-Ampakleng Road.
Appropriation: P83M
Contract Cost: P76,987,155.99
Length: 4,722.71 mts.
Width: 6.10 mts.
Contractor: Agafer Construction and Trading
Duration: 192 Calendar days
Date Started: July 8, 2021
Expiry Date: January 15, 2022

Bagabag
Upgrading of Kinacao-Kurasay-Kinalabasa Road.
Appropriation: P34M
Contract Cost: P32,544,065.31
Length: 1,957.876 mts.
Width: 6.10 mts.
Contractor: Triple P Construction
Duration: 161 Calendar days
Date Started: July 8, 2021
Expiry Date: December 15, 2021

Quezon & Bagabag
Upgrading of Bonifacio-Dagupan-Palayan Road.
Appropriation: P127M
Contract Cost: P121,572,118.68
Length: 6,246.33 mts.
Width: 6.10 mts.
Contractor: FB Bantales Engineering Construction/Ambaguio Builders (Joint Venture)
Duration: 396 Calendar days
Date Started: July 8, 2021
Expiry Date: August 7, 2022

Quezon
Upgrading of Diffuday-Bonifacio Road.
Appropriation: P42.5M
Contract Cost: P450,083,124.68
Length: 2,165.15 mts.
Width: 6.10 mts.
Contractor: Agafer Construction and Trading
Duration: 166 Calendar days
Date Started: July 8, 2021
Expiry Date: December 20, 2021